在搭设木工加工棚时要了解到施工要点
由于木工加工棚的施工质量会对后期使用的产生较大影响,因此,在搭设木工加工棚的过程中应注意以下施工要点。
Since the construction quality of woodworking shed will have a great impact on the safety of later use, the following construction points should be paid attention to during the erection of woodworking shed.
(1)施工前,应先编制详细的木工加工棚施工方案,并在开始施工时先对木工加工棚范围内的两侧道路进行整平、拓宽作业,设置排水沟,以确保排水畅通,适应吊车站位及吊装。
(1) Before construction, a detailed construction plan for the woodworking shed shall be prepared. At the beginning of construction, the roads on both sides of the woodworking shed shall be leveled and widened, and drainage ditches shall be set to ensure smooth drainage and adapt to the crane station and hoisting.
(2)若木工加工棚的基础施工范围内光缆、电力线众多,还应制订光缆、电力线等设备的改移方案,以及相关保护措施,以确保施工和设备。
(2) If there are many optical cables and power lines within the foundation construction scope of the woodworking processing shed, the relocation scheme of optical cables, power lines and other equipment, as well as relevant protective measures, should also be formulated to ensure construction safety and equipment safety.
(3)木工加工棚施工时,其焊接作业的过程一定要注意防火,如果有风必须设置好挡风板,以免发生火花飞溅,造成隐患。同时,木工加工棚上不得堆放杂物,以及钢筋、模板等材料,以防发生火灾。
(3) During the construction of the woodworking shed, attention must be paid to fire prevention during the welding operation. If there is wind, the wind deflector must be set up to prevent sparks from splashing and causing potential safety hazards. At the same time, no sundries, reinforcement, formwork and other materials shall be stacked on the woodworking shed to prevent fire.
(4)按木工加工棚的矩型管立杆间距、排距要求进行定位放线,并将垫板铺设放平稳,不得悬空。同时,矩型管立杆接长应采用对接电焊连接,立杆对接电焊焊接应交错布置。
(4) The positioning and setting out shall be carried out according to the requirements for the spacing and row spacing of rectangular pipe poles in the woodworking shed, and the base plate shall be laid stably and shall not be suspended. At the same time, the extension of rectangular pipe upright shall be connected by butt welding, and the butt welding of upright shall be staggered.
(5)木工加工棚棚顶铺装施工时,均应在既有线上方作业,且须注意高空作业,严禁任何机具和材料意外掉落损坏线路设备。同时,应通过钢管立柱,在木工加工棚两侧设置接地措施。
(5) When paving the roof of the woodworking shed, work above the existing line, and pay attention to the safety of working at heights. It is strictly forbidden to accidentally drop any machines and materials to damage the line equipment. Meanwhile, grounding measures shall be set on both sides of woodworking shed through steel pipe column.
此外,木工加工棚在搭设完成后,施工单位应先组织领导小组组长及员、质检员等进行验收,自检合格后报请监理单位进行验收,验收合格后方可进行使用。更多相关内容就来我们网站//www.hongdaxinwuliu.com咨询吧!
In addition, after the woodworking shed is erected, the construction unit shall first organize the leader of the safety leading group, the safety officer, the quality inspector, etc. to carry out acceptance. After the self inspection is qualified, the woodworking shed shall be submitted to the supervision unit for acceptance. The woodworking shed can only be used after the acceptance is qualified. More relevant content will come to our website //www.hongdaxinwuliu.com Consult!
- 上一篇:哪些施工现场须要设置临边防护