浅析搭设临边防护栏时符合的要求
防护栏的作用是非常大的,而在临时搭设临边护栏时也是要符合要求的,那么一起来了解一下搭设临边防护栏时符合的要求。
The role of protective fence is very great, and the temporary erection of edge protective fence should also meet the safety requirements. Let's learn about the requirements met when erecting edge protective fence.
(1)防护栏杆应由上、下两道横杆及栏杆柱组成,上杆离地面高度为10--12m,下杆离地面高度为05--06m。坡度大于1:22的屋面,防护栏杆应高15m,并加挂网。除经设计计算外,横杆长度大于2m时,须加设栏杆柱。
(1) The protective railing shall be composed of upper and lower cross bars and railing posts. The height of the upper bar from the ground is 10-12m, and the height of the lower bar from the ground is 05-06m. For roofs with a slope greater than 1:22, the protective railings shall be 15m high, and safety nets shall be hung. In addition to the design calculation, when the length of the cross bar is greater than 2m, balusters must be added.
(2)栏杆柱的固定应符合下列要求:
(2) The fixing of railing posts shall meet the following requirements:
当在基坑四周固定时,可采用钢管并打入地面50--7Ucm深。锕管离过日时距离,不应小于50cm。当基坑周边采用板桩时,钢管可打在板桩外侧。
When fixing around the foundation pit, steel pipes can be used and driven into the ground 50-7ucm deep. Actinide tubes should be no less than 50cm away from the transit time. When sheet piles are used around the foundation pit, steel pipes can be driven outside the sheet piles.
当在混凝土楼面、屋面和墙面固定时,可用预埋件与钢管或钢筋焊牢。采用竹、木栏杆时,可在预埋件上焊接30cm长的L50~5角钢,其上下各钻一孔,然后用lOmm螺栓与竹、木杆件拴牢。
When fixed on the concrete floor, roof and wall, embedded parts can be welded firmly with steel pipes or reinforcement. When bamboo and wood railings are used, l50~5 angle steel with a length of 30cm can be welded on the embedded parts, with a hole drilled up and down, and then fastened to the bamboo and wood members with a bolt of 10mm.
当在砖或砌块等砌体上固定时,可预先砌入规格相适应的806弯转扁钢作预埋铁的混凝土块,然后用上述方法固定。
When fixing on bricks or blocks, 806 bending flat steel with appropriate specifications can be built in advance as the concrete block of embedded iron, and then fixed with the above method.
(3)栏杆柱的固定及其与横杆的连接,其整体构造应使防护栏杆在上扦任何处,能经受任何方向的1000N外力。当栏杆所处位置有发生人群拥挤、车辆冲击或物件碰撞等可能时,应加大横杆截面或加密柱距。
(3) The overall structure of the fixing of the railing and its connection with the cross bar shall enable the protective railing to withstand 1000N external force in any direction anywhere on the upper cutting. When the position of the railing has the possibility of crowd congestion, vehicle impact or object collision, the cross-section of the cross bar should be increased or the column spacing should be densified.
(4)防护栏杆须自上而下用安垒立网封闭,或在栏杆下边设置严密固定的高度不低于18cm的挡脚板或40cm的挡脚笆。挡脚板与挡脚笆上如有孔眼,不应大于25ram。板与笆下边距离底面的空隙不应大于lOmm。接料平台两侧的栏杆,须自上而下加挂立同或满扎竹笆。
(4) The protective railing must be closed with a safety net from top to bottom, or a tightly fixed toe board with a height of not less than 18cm or a 40cm toe fence should be set under the railing. If there is a hole on the toe board and toe fence, it should not be greater than 25ram. The gap between the board and the lower edge of the fence and the bottom surface shall not be greater than 10 mm. The railings on both sides of the receiving platform must be hung with safety poles or bamboo fences from top to bottom.
⑸当临边的外侧面临街道时,除防护栏杆外,敞口立面须采用满挂网或其他可靠措施作全封闭处理。
(5) when the outer side of the edge faces the street, in addition to the protective railings, the open facade must be fully enclosed by full hanging safety nets or other reliable measures.
以上就是搭设临边防护栏时符合的要求相关介绍,想了解更多的相关信息,欢迎关注我们网站//www.hongdaxinwuliu.com进行咨询了解吧。
The above is the relevant introduction of the requirements met when setting up the edge guard. If you want to know more relevant information, please follow our website //www.hongdaxinwuliu.com Consult and understand.
- 上一篇:施工围挡厂家讲解围挡选择哪种很实用
- 下一篇:临边防护栏的施工需要注意的事项